page 1
page 2
page 3
page 4
page 5
page 6
page 7
page 8
page 9
page 10
page 11
page 12
page 13
page 14
page 15
page 16
page 17
page 18
page 19
page 20
page 21
page 22
page 23
page 24
page 25
page 26
page 27
page 28
page 29
page 30
page 31
page 32
page 33
page 34
page 35
page 36
page 37
page 38
page 39
page 40
page 41
page 42
page 43
page 44
page 45
page 46
page 47
page 48
page 49
page 50
page 51
page 52
page 53
page 54
page 55
page 56
page 57
page 58
page 59
page 60
page 61
page 62
page 63
page 64
page 65
page 66
page 67 page 68
page 69
page 70
page 71
page 72
page 73
page 74
page 75
page 76
page 77
page 78
page 79
page 80
page 81
page 82
page 83
page 84
page 85
page 86
page 87
page 88
page 89
page 90
page 91
page 92
page 93
page 94
page 95
page 96
page 97
page 98
page 99
page 100
page 101
page 102
page 103
page 104
page 105
page 106
page 107
page 108
page 109
page 110
page 111
page 112
page 113
page 114
page 115
page 116
page 117
page 118
page 119
page 120
page 121
page 122
page 123
page 124
page 125
page 126
page 127
page 128
page 129
page 130
page 131
page 132
page 133
page 134
page 135
page 136
page 137
page 138
page 139
page 140
page 141
page 142
page 143
page 144
page 145
page 146
page 147
page 148
page 149
page 150
page 151
page 152
page 153
page 154
page 155
page 156
page 157
page 158
page 159
page 160
page 161
page 162
page 163
page 164
page 165
page 166
page 167
page 168
page 169
page 170
page 171
page 172
page 173
page 174
page 175
page 176
page 177
page 178
page 179
page 180
page 181
page 182
page 183
page 184
page 185
< prev - next > Energy Hydro power civil_works_guidelines_for_micro_hydro (Printable PDF)
CIVIL WORKS GUIDELINES FOR MICRO-HYDROPOWER IN NEPAL
65
2. Design water level in gravel trap
This should be at least 0.49 m + 10% (safety margin) i.e. 0.54 m below the low river level at the intake, or “a” = 0.54 m in Figure 4.11.
3. Flood flow through intake pipes
Flood level is 1.5 m above low river level.
Allow 0.2 m head over gravel trap spillweir (i.e. b = 0.2 m in Figure 4.11).
Then net head on intake pipes = 0.54 + 1.5 - 0.2 = 1.84 m., or “c” = 1.84 in Figure 4.11.
Trial and error solution for flow:
a) Try
Q = 200 1/s in each pipe
or, 1.2Q / d = 1.2x0.2 / 0.262 = 0.916
or, f = 0.0152 (from Moody Chart)
or, hwall loss = 0.0152x40x0.202 / 12x0.2622 = 1.64m
V = 4Q / IId2 = 4x0.2 / IIx0.2622 = 3.71 m/s
Inlet & exit losses (0.8 + 1.0) V2 / 2g = 1.26m
Total head loss = 2.90m
This is more than 1.84 m (net head on intake pipes for flood level),
... assumed flow is too high.
Try interpolating : 200 1/s (1.84/2.90)1/2 = 159 1/s
b) Check for Q = 159 1/s in each pipe.
or, 1.2Q / d = 1.2x0.159 / 0.262 = 0.730
or, f = 0.0154 (from Moody Chart)
or, hwall loss = 0.0154x40x0.1592 = 1.05m
Inlet and exit losses (0.8+1.0) V2 / 2g = 0.80m
Total head loss = 1.85m
This is near enough to 1.84 m
Therefore flood flow through the two intake pipes is: 2 x 159 1/s =
318 1/s
4. Spillway length at gravel trap
Weir equation:
Qspillway = Cw x Lspillway x (hovertop)1.5
... Required spillway weir length,
Lspillway = Qspillway / Cw x (hovertop)1.5
Take Cw = 1.6 and Qspillway = 318 1/s to allow the entire flood flow to
be spilled over in case the turbine needs to be closed during such
floods.
hovertop = 0.20 m (head over weir, assumed earlier)
... Lspillway = 0.318 / 1.6x0.201.5 = 2.22m
or ‘d‘ = 2.22 m in Figure 4.11.
Note the following:
1. To limit the inlet velocity, two parallel pipes have
been used from the intake to the gravel trap. Down-
stream of the gravel trap there is only one pipe
and the velocity is doubled. The reason for using
a lower velocity in the initial pipe length was to
lower the submergence head so that excavation
work at the intake could be minimised. With lower
inlet velocity there less chance of attracting float-
ing debris which could block the inlet.
2. The spillway weir length is reasonable, but note
that an alternative assumption for head over the
weir would give a different answer. The walls
around the gravel trap must be high enough to
contain the flood flow over the spillweir.
3. The gravel trap has to be located sufficiently far
downstream of the intake to ensure that the gravel
trap spillweir is above the maximum river flood
level at that point: in this case the 40 m intake pipe
length is more than enough to meet this criterion.